Skip to main content
DigitalOcean is a cloud platform that provides a range of services for building and deploying applications. This guide deploys a Bun HTTP server to DigitalOcean using a Dockerfile.
Before continuing, make sure you have:

1

Create a new DigitalOcean Container Registry

Create a new Container Registry to store the Docker image.
In the DigitalOcean dashboard, go to Container Registry, and enter the details for the new registry.
DigitalOcean registry dashboard
Make sure the details are correct, then click Create Registry.
You should see the new registry in the DigitalOcean registry dashboard:
DigitalOcean registry dashboard
2

Create a new Dockerfile

Create a new Dockerfile in the root of your project. This file contains the instructions to initialize the container, copy your local project files into it, install dependencies, and start the application.
Dockerfile
Make sure that the start command corresponds to your application’s entry point. The start command can also be CMD ["bun", "run", "start"] if you have a start script in your package.json.If your app doesn’t have dependencies, you can omit the COPY package.json bun.lock ./ and RUN bun install --production --frozen-lockfile lines. Bun doesn’t write a bun.lock for a project with no dependencies.
Create a new .dockerignore file in the root of your project. It lists the files and directories to exclude from the container image, such as node_modules. Excluding them keeps builds faster and smaller:
.dockerignore
3

Authenticate Docker with DigitalOcean registry

Before building and pushing the Docker image, authenticate Docker with the DigitalOcean Container Registry:
terminal
This command authenticates Docker with DigitalOcean’s registry using your DigitalOcean credentials. Without this step, the build and push command fails with a 401 authentication error.
4

Build and push the Docker image to the DigitalOcean registry

Make sure you’re in the directory containing your Dockerfile, then build and push the Docker image to the DigitalOcean registry in one command:
terminal
If you’re building on an ARM Mac (M1/M2), you must use docker buildx with --platform=linux/amd64 for compatibility with DigitalOcean’s infrastructure. Using docker build without the platform flag creates an ARM64 image that won’t run on DigitalOcean.
Once the image is pushed, you should see it in the DigitalOcean registry dashboard:
DigitalOcean registry dashboard
5

Create a new DigitalOcean App Platform project

In the DigitalOcean dashboard, go to App Platform > Create App. You can create a project directly from the container image.
DigitalOcean App Platform project dashboard
Make sure the details are correct, then click Next.
DigitalOcean App Platform service dashboard
Review and configure resource settings, then click Create app.
DigitalOcean App Platform service dashboard
6

Visit your live application

Your app is now live. Once the app is created, you should see it in the App Platform dashboard with its public URL.
DigitalOcean App Platform app dashboard